The municipal housing company Ginsheim-Gustavsburg (KWG) is planning a new residential complex with 20 apartments on the site Stegstraße 27-33, which has become vacant after the demolition of the aging existing building, on the south-eastern edge of the Ginsheim district.

Project start for Elektro: March 2023

Planned completion: Dec 2023

Project description

Electrical installation for:

Power installations :

  • distributions,
  • power cables,
  • emergency lighting,
  • routes, channels, floor tanks,
  • main and control cables,
  • installation equipment,
  • equipotential bonding,
  • interior lighting,
  • exterior lighting

Low power installation

  • fire alarm system,
  • cabling weak current,
  • antenna system,
  • EDV / TK network,
  • ELA system